HomeMy WebLinkAbout95-01 - ADMIN Resolution - Economic Development Authority - 1995/02/06RESOLUTION NO. EDA 95-1
RESOLUTION PERTAINING TO CHANGE ORDER NO. 4
WITH ADOLFSON & PETERSON, INC.
FOR EDA CONTRACT NO. 8-93
WHEREAS, the Economic Development Authority entered into EDA Contract No.
8-93 with Adolfson & Peterson, Inc. for the construction of the Tower Place
parking ramp; and
WHEREAS, the Economic Development Authority has determined that certain
modifications be made to the contract to facilitate the construction of the project,
said modifications being as follows:
Three deductions, 28 additions, five no -cost items, and one negotiated
settlement credit to the project as described in the attached narrative for
Change Order No. 4, and
WHEREAS, the contractor, Adolfson & Peterson, Inc., has agreed to the prices
for the modifications referenced above,
NOW, THEREFORE, BE IT RESOLVED by the St. Louis Park Economic
Development Authority that the above modifications to EDA Contract No. 8-93
are approved; and
BE IT FURTHER RESOLVED by the St. Louis Park Economic Development
Authority that the increase of $98,000 to the project is accepted.
Adopted by the Economic Development Authority February 6, 1995
Lyle W. Hanks
President
A�-� �ti
Charles W. Meyer
Executive Director