HomeMy WebLinkAbout18-121 - ADMIN Resolution - City Council - 2018/08/20Resolution No. 18-121 Resolution authorizing final payment and accepting work for the alley reconstruction project City project no. 4017-1500 Contract no. 74-17 Now therefore be it resolved by the City Council of the City of St. Louis Park, Minnesota, as follows: 1. Pursuant to a written contract with the city dated May 15, 2017, G.L. Construction Inc. has satisfactorily completed the annual alley reconstruction project, as per contract no. 74-17. 2. The Engineering Director has filed her recommendations for final acceptance of the work. 3. The work completed under this contract is accepted and approved. The final contract cost is $379,754.94. 4. The City Manager is directed to make final payment on the contract, taking the —contractor's receipt in full. for Administration: AO—Upted bey -the City Council August 20, 2018 ThorWs K! qh!`m in , City Manager Attest: