HomeMy WebLinkAbout1993/03/15 - ADMIN - Agenda Packets - Economic Development Authority - RegularAGEN DA
ECONOM IC DEVELOPM ENT AUT HOR IT Y
ST. LOUIS PARK, MINNESOTA
March 15, 1993
1. Call to order
2. Roll call
/C
4. Approval of March 15, 1993 agenda ~/f--t1/\
5. Reports
a. was Pontiac d ate gCD -o
Ge rec fl)
3. Approval of March l, 1993 minutes
6. Unfinished business
7. New business
8. Communications and bills
9. Adjournment• 7;/2
REQUEST- FOR EDA ACTION
DATE March 15, 1993 ____ ___,_ _
AGENDA SECTION: Reports
NO. 5
ORIGINATING DEPARTMENT:
Public Works
ITEM:
NO. 5a
Wilkins Pontiac Site - Update
APPROVED: <n ,. ),
James N. Grube/ <
Director of Public Works
)
Synopsis: This report. provides an update on the demolition activities at the
Wilkins Pontiac site and recommends that the Economic Development Authority
(EDA) authorize execution of a contract amendment with STS Consultants Ltd
(STS) for work at the site and authorize execution of an agreement with the
Minnesota Pollution Control Agency (MPCA) to provide for removal of hazardous
materials from the site.
Background: On August 25, 1992 Wilkins Pontiac (Wilkins) notified the EDA of
its intent to vacate its site at 5100 Excelsior Boulevard on or about
September 30. On September 8, the EDA considered a staff report which
summarized the findings of a 1991 environmental assessment conducted on the
Wilkins site by STS on behalf of the EDA. The staff report indicated the
Wilkins site contained at least:
2 underground gasoline tanks
1 underground fuel oil tank
1 underground used oil storage tank
soils impacted by a fuel oil spill
soils impacted by lead and volatile organic compounds (VOC)
asbestos containing materials
site drainfield
hydraulic reservoir tanks
The September 8, 1992 staff report concluded with a recommendation that the
EDA authorize staff to solicit a proposal from STS for the design and
inspection/ administration of site demolition activities to render the site
available for redevelopment in 1993. On October 5, the EDA awarded a contract
in the amount of $43,300 to STS for oversight of the activities noted above.
Discussion: To date STS has provided oversight for the removal of the four
underground tanks, excavation of soils impacted by a fuel oil spill,
excavation of soils suspected to be impacted by VOC's and lead, and removal of
hydraulic fluid from the hydraulic tanks. In addition, STS is supervising the
removal of asbestos containing material (scheduled completion - end of March),
and completing specifications for the demolition of the Wilkins building
(contract award date - April 19, 1993).
(continued)
PUBLIC WORKS Executive Director
APPROVAL. APPROVAL APPROVAL APPROVAL !APPROVAL ,// /
< so lograwfso loom#en [oonwen [osmane /-<
COUNCIL ACTION: MOTION BY 2N D BY TO
>
Although much has been accomplished to date two additional tasks (in addition
to building demolition) must be completed. The first task is the disposal of
fuel oil impacted soils, and the second is the excavation and disposal of
soils moderately impacted by lead and soils heavily impacted by lead and
cadmium.
The disposal of the fuel oil impacted soils is a straight forward task.
Approximately 100 cubic yards of impacted soil has been stockpiled at the
site, and preparations are underway to have the material hauled to a local
contractor yard for incineration under the oversight of the MPCA.
Approximately 10 cubic yards of impacted soil remain in place beneath the
building foundation, and the building demolition contract provides for its
removal.
The existence of soils heavily impacted by lead and cadmium was discovered by
STS as it supervised the removal of other voe and lead impacted soils located
north of the Wilkins building. As removal of the voe and lead impacted soils
progressed, STS encountered soils which were visibly stained; therefore it
halted the soil removal activity. Subsequent laboratory analyses indicated
the (approximately) 30 cubic yards of material excavated from the site
contained elevated lead levels which will necessitate their disposal as
contaminated (through not hazardous) materials. However, samples taken from
the bottom and sides of the excavation indicate the in-place soils have been
heavily impacted by lead and cadmium. In addition, what appears to be small,
old automobile parts were encountered. STS and staff are of the opinion the
lead and cadmium are the result of parts washing with cutting fluids or
discard of used oil. The presence of old automobile parts tends to support
the opinion.
Based on initial STS estimates, it appears that approximately 15 cubic yards
of soil may contain lead and cadmium at concentration levels exceeding
established thresholds; therefore, the material appears to be hazardous.
Recent discussions with MPCA staff indicate the EDA has two options:
1. Remove the 15 cubic yards of lead/cadmium impacted soils under the
MPCA's Property Transfer/Technical Assistance program.
2. Remove the 15 cubic yards of lead/cadmium impacted soils under the
conventional State and Federal Superfund programs.
Staff favors the MPCA's Property Transfer/Technical Assistance program because
the scope of the clean up task is clearly identified-approximately 15 cubic
yards of impacted soils must be removed. In addition, since the groundwater
is nearly 15 feet below the impacted soils, contamination is confined to a
relatively small, manageable area.
If the EDA elects to enter the conventional Superfund program, more studies
will be required, and the more formal process will almost guarantee that the
soils will not be removed in 1993.
In order to provide for the timely removal and disposal of the heavily
impacted soils, it is recommended that the EDA authorize staff to work with
/ the MPCA under its Property Transfer/Technical Assistance program.
(continued)
Financial Considerations: The EDA budget for the preparation of the Wilkins
site for redevelopment was initially established at $258,000. A review of the
project budget to date is as follows:
Budgeted Actual/Estimated
Task Amount Amount
Engineering $ 54,000 $ 43,300 (Actual - A)
Tank removals 13,000 12,570 (A)
Fuel oil impacted soi 1 s 23,000 6,000 (Estimated - E)
Lead contaminated soils 25,000 6,000 (E)
Lead/cadmium soils 15,000 (E)
Asbestos removal 41,000 16,185 (A)
Miscellaneous 7,000 7,000 (E)
Building demolition 95.000 95.000 (E)
Total $258,000 $201,055
Although it appears that the site preparation activities remain within budget,
staff has identified two areas where costs will increase:
1. STS has submitted a request for an additional $12,020 to cover costs
experienced and anticipated.
2. The MPCA will charge the EDA for MPCA staff costs it will experience as
it supervises the EDA within the Property Transfer/Technical Assistance
program (EDA staff estimate - $8,000).
Regarding STS' fees, the firm has indicated it has incurred $1,320 in
additional costs related to supervision of the removal of hydraulic fluid from
hydraulic fluid reservoirs in the Wilkins building ($1,035) and related to
additional soil exploration activity in the vicinity of the fuel oil spill
site ($285). Staff considers the STS request to be valid insofar as each
activity is beyond the scope of the present contract.
In addition to the $1,320 claim above, STS has indicated that it will incur an
additional $10,700 in the removal of the lead/cadmium soils and documentation
related thereto. Again, staff considers the STS request to be valid, as the
activities are not within the scope of the present contract.
Regarding the MPCA costs, EDA staff is of the opinion that $8,000 is a
reasonable "high end" estimate for the scope of the project. Staff
anticipates that the majority of the MPCA costs will be incurred in document
review and the drafting of a "no action letter" by the MPCA. The "no action"
letter will acknowledge the EDA's efforts and success at remediating the
lead/cadmium problem.
Given the information available to date, it appears the total site preparation
budget will approach $221,000 or approximately $37,000 less than the
established budget.
Recommendation: It is recommended the Economic Development Authority
authorize execution of an amendment to its contract with STS Consultants Ltd
for Wilkins Pontiac site activities increasing the contract amount from
$43,300 to $55,320, and authorizing execution of an agreement with the
Minnesota Pollution Control Agency for the handling of lead/cadmium hazardous
materials under the State's Property Transfer/Technical Assistance program.
cmr
Inter-Office
INFORMATION ONLY
Memorandum
City of St. Louis Park
TO:
FROM:
DATE:
SUBJECT:
Economic Development Authority
Clint Pires, Interim Executive Director{!__
March 15, 1993
Park Nicollet Environmental Reports
)
As of March 9, 1993, the Minnesota Pollution Control Agency (MPCA) had
received and reviewed Park Nicollet's environmental reports. In general,
the MPCA appears to agree with the conclusions of the reports and remedial
actions included therein. The EDA attorneys and City staff are al so generally
comfortable with remedial actions outlined in the reports. EDA environmental
attorney, Karen Hansen, and Jim Grube will continue to work now at gaining
additional protections for the EDA and City during and following project
activity.
The MPCA intends to hold meetings with businesses (i.e., AAA, Byerly's
and Wayside House) as well as Wolfe Lake Condominiums to explain study
findings, safety and recommended remediation steps. The EDA, City, Park
Nicollet and MPCA will work on these meetings jointly. The EDA will be
presented with final report findings and implications and informed once
the MPCA has scheduled such meetings.
It is anticipated that the Commissioner of the MPCA may sign off on the
Park Ni coll et reports as soon as March 15. It does appear at this ti me
that the project will continue forward with whatever additional activities
may be required as a result of remediation.
It should be noted that working through many of these environmental and
legal issues has been and will continue to be a challenge. All involved
in this project from the City staff and EDA attorney's office have done
an exceptional job. Of particular note on the environmental issues is the
work of Karen Hansen and Jim Grube. Their expertise in protecting the interests
of the EDA while at the same ti me working to move this project along have
been necessary and invaluable.