HomeMy WebLinkAbout13-118 - ADMIN Resolution - City Council - 2013/08/19RESOLUTION NO. 13-118
RESOLUTION AUTHORIZING FINAL PAYMENT IN THE
• AMOUNT OF $7,567.60.00 AND ACCEPTING THE HOLLOW METAL FRAMES,
DOORS AND FINISH HARDWARE WORK FOR
FIRE STATIONS NO. 1 AND NO. 2 WITH BREDEMUS HARDWARE CO., INC.
CITY PROJECT NO. 2008-3001 AND 2008-3002
CONTRACT NO. 41-11
NOW THEREFORE BE IT RESOLVED, by the City Council of the City of St. Louis
Park, Minnesota, as follows:
1. Pursuant to a written contract with the City dated April 12, 2011, Albers Mechanical
Contractors, Inc. satisfactorily completed Work Scope 10 (Hollow Metal Frames, Doors and
Finish Hardware) for Fire Stations No. 1 and No. 2, as per Contract No. 41-11.
2. The Construction Manager, Kraus -Anderson Construction Company, recommends final
acceptance of the work.
3. The work completed under this contract is accepted and approved. The City Manager is
directed to make final payment on the contract, taking the contractor's receipt in full.
Original Contract Price
Change Order #1
Change Order #2
Final Contract Amount
Previous Payments
Balance Due
Review -\ ministration:
WAVE
If
City Mana'r J
Attest:
City Clerk
Ad
$148,735.00
$917.00
$1,700.00
$151,352.00
($143,784.40)
$7,567.60
y the City Council August 19, 2013
Mayor