HomeMy WebLinkAbout12-164 - ADMIN Resolution - City Council - 2012/11/05RESOLUTION NO. 12-164
RESOLUTION AUTHORIZING FINAL PAYMENT
IN THE AMOUNT OF $51,536.02 AND ACCEPTING THE WORK FOR THE
WATER TREATMENT PLANT NO. 6 REHABILITATION PROJECT
WITH MAGNEY CONSTRUCTION, INC.
CITY PROJECT NO. 2010-1300
CONTRACT NO. 177-11
BE IT RESOLVED by the City Council of the City of St. Louis Park, Minnesota, as
follows:
1. Pursuant to a written contract with the City dated January 3, 2012, Magney Construction,
Inc. has satisfactorily completed the Water Treatment Plant No. 6 Rehabilitation Project,
as per Contract No. 177-11.
2. The Director of Public Works has filed his recommendations for final acceptance of the
work.
3. The work completed under this contract is accepted and approved. The City Manager is
directed to make final payment on the contract, taking the contractor's receipt in full.
Reviewed
Original Contract Amount
Change Orders
Final Contract Amount
Previous Payments
Balance Due
o Administration:
City M
Attest:
_n Griy��
City Clerk �1
$ 708,000.00
$ 15,222.12
$ 723,222.12
$ 671,686.10
$ 51,536 02