HomeMy WebLinkAbout12-023 - ADMIN Resolution - City Council - 2012/02/06RESOLUTION NO. 12-023
RESOLUTION ACCEPTING WORK FOR THE
MSC RENOVATION PROJECT CITY PROJECT 2008-900
CONTRACT NO. 79-09
NOW THEREFORE BE IT RESOLVED, by the City Council of the City of St. Louis
Park, Minnesota, as follows:
1. Pursuant to a written contract with the City dated July 6, 2009 Jorgenson
Construction, Inc. has satisfactorily completed all renovation and construction work at
the MSC and Creekside Park per Contract No. 79-09.
2. The Director of Inspections has filed his recommendations for final acceptance of work.
3. The work completed under this contract is accepted and approved. The City Manager
is directed to make final payment on the contract, taking the contractor's receipt in full.
Original Contract Price $8,164,000.00
Deducts (111,857.94)
Additions 339,232.00
Revised Contract Amount $8,391,374.06
Payment 1
Payment 2
Payment 3
Payment 4
Payment 5
Payment 6
Payment 7
Payment 8
Payment 9
Payment 10
Payment 11
Payment 12
Payment 13
Total Previous Payments
Final Payment
Total Contract Cost
Revi fo • dmmistration:
A 1
1111i11111111
City
$ 269,990
555,275
687,610
1,003,295
1,451,600
591,660
444,410
836,665
760,570
668,895
454,575
277,495
172,808.50
$8,174,848.50
$ 216,525.56
$8,391,374.06
Ado • ted by the City Council February 6, 2012
Attest:
Th
City Clerk