HomeMy WebLinkAbout11-023 - ADMIN Resolution - City Council - 2011/02/07RESOLUTION NO. 11-023
RESOLUTION AUTHORIZING FINAL PAYMENT IN THE
AMOUNT OF $97,990.80 AND ACCEPTING THE WORK FOR THE
2010 LOCAL STREET REHABILITATION PROJECT
WITH VALLEY PAVING, INC.
CITY PROJECT NO. 2009-1000
CONTRACT NO. 52-10
NOW THEREFORE BE IT RESOLVED, by the City Council of the City of St. Louis
Park, Minnesota, as follows:
1. Pursuant to a written contract with the City dated April 19, 2010, Valley Paving, Inc. has
satisfactorily completed the 2010 Local Street Rehabilitation Project, as per Contract No. 52-10.
2. The Director of Public Works has filed his recommendations for final acceptance of the work.
3. The work completed under this contract is accepted and approved. The City Manager is directed
to make final payment on the contract, taking the contractor's receipt in full.
Revie
Original Contract Price $ 1,005,620.31
Change Order 1 $ 19,141.25
Change Order 2 .00
Change Order 3 $ 13,249.05
Underrun $ (25,205.90)
Contract Amount $1,012,804.71
Previous Payments $ 914,813.91
Balance Due $ 97,990.80
for A inistration:
City
Attest:
City Clerk
Adopted by the City Council February 7, 2011
Mayor