HomeMy WebLinkAbout10-113 - ADMIN Resolution - City Council - 2010/10/18•
RESOLUTION NO. 10-113
RESOLUTION AUTHORIZING FINAL PAYMENT IN THE
AMOUNT OF $3,800.00 AND ACCEPTING THE EARTH WORK
FOR RECONSTRUCTION OF FERN HILL PARK
WITH G L CONTRACTING, INC.
CITY PROJECT NO. 20080070
CONTRACT NO. 112-08
BE IT RESOLVED by the City Council of the City of St. Louis Park, Minnesota, as
follows:
1. Pursuant to a written contract with the City dated September 16, 2008, G L Contracting,
Inc. has satisfactorily completed the earthwork for reconstruction of Fern Hill Park, as per Contract
No. 112-08.
2. The Director of Parks and Recreation has filled her recommendations for final acceptance of
the work.
II3. The work completed under this contract is accepted and approved. The City Manager is
dir cte• o make final payment on the contract, taking the contractor's receipt in full.
Revi - ed
ministration:
Ci
Attest:
Adopted by �he City Council October 18, 2010
May, r
A,