RESOLUTION NO. 10-110
RESOLUTION AUTHORIZING FINAL PAYMENT IN THE AMOUNT OF
$121,144.30 FOR THE PARK PLACE BOULEVARD IMPROVEMENT PROJECT,
CITY PROJECT NO. 2007-1101, CONTRACT NO. 72-08
NOW THEREFORE BE IT RESOLVED by the City Council of the City of St. Louis Park,
Minnesota, as follows:
1. Pursuant to a written contract with the City dated June 2, 2008, Valley Paving, Inc. has satisfactorily
completed the Park Place Boulevard Project as per Contract No. 72-08.
2. Change Order No. 4 in the amount of $11,500.00 is hereby approved.
2. The Director of Public Works has filed his recommendations for final acceptance of the work.
3. The work completed under this contract is accepted and approved. The City Manager is directed to
make final payment on the contract, taking the contractor's receipt in full.
Original Contract Price $4,038,465.97
Change Order No. 1 $210,964.64
Change Order No. 2 $47,146.61
Change Order No. 3 $19,360.00
Change Order No. 4 $11,500.00
Total Contract $4,327,437.22
Total Completed $4,264,882.01
Previous Payments
Balance Due
Revi' - A•Mlil► AIM inistration:
i�llll
City MVa;,e
Attest:
�Yt u
ill City Clerk
$4,143,737.71
$121,144.30
Adopted b1 the City Council October 18, 2010