RESOLUTION NO. 09-038
RESOLUTION ACCEPTING WORK ON
2008 SIDEWALK, CURB & GUTTER MAINTENANCE PROJECT
CITY PROJECT NO. 2008-0003, 0004, & 2009-0004
CONTRACT NO. 73-08
NOW THEREFORE BE IT RESOLVED, by the City Council of the City of St. Louis Park,
Minnesota, as follows:
1. Pursuant to a written contract with the City dated June 2, 2008, Concrete Idea, Inc. has satisfactorily
completed the sidewalk, curb & gutter maintenance project, as per Contract No. 73-08.
2. The Director of Public Works has filed his recommendations for final acceptance of the work.
3. The work completed under this contract is accepted and approved. The City Manager is directed to
make final payment on the contract, taking the contractor's receipt in full.
Original Contract Price $104,754.00
Change Order 00
Overrun $ 34,937.25
Previous Payments $ 79,513.34
Balance Due
Revi d for Administration:
"Ada wom
City a aver V
Attest:
1,c1 'ketC5%
City Clerk
$60,177.91
Adopted by the City Council March 2, 2009