HomeMy WebLinkAbout05-006 - ADMIN Resolution - City Council - 2005/01/03RESOLUTION NO. 05-006
RESOLUTION ACCEPTING WORK ON
EXCELSIOR BOULEVARD RECONSTRUCTION PROJECT
CITY PROJECT NO. 99-05
CONTRACT NO. 35-02
HARDRIVES, INC.
BE IT RESOLVED by the City Council of the City of St Louis Park, Minnesota, as
follows.
1. Pursuant to a written contract with the City dated Apnl 15, 2002, Hardnves, Inc. has
satisfactorily completed the Excelsior Boulevard reconstruction project, as per Contract No
35-02
2 The Director of Public Works has filed his recommendations for final acceptance of the
work.
3. The work completed under this contract is accepted and approved. The City Manager is
directed to make final payment on the contract, taking the contractor's receipt in full.
Original Contract Pnce
$1,766,900 35
Change Order
$85,292.30
Over run/Extra work
$152,459.52
Final Contract Pnce
$2,004,652.17
Previous Payments
($1,888,952.07)
Balance Due
$115,700.10
Rev e ed for Administration
I �►I1��
City Manager
Attest:
roteby the City Council January 3, 2005
Ma or
lg