HomeMy WebLinkAbout144 - ADMIN Resolution - City Council - 2003/10/07RESOLUTION NO. 144
RESOLUTION ACCEPTING WORK ON
EXCELSIOR BOULEVARD, PHASE 2 CONSTRUCTION
MONTEREY AVENUE TO FRANCE AVENUE
CITY PROJECT NO. 96-22
CONTRACT NO. 14-98
BE IT RESOLVED by the City Council of the City of St. Louis Park, Minnesota, as follows:
1. Pursuant to a written contract with the City dated April 6, 1998, Hardrives, Inc. has
satisfactorily completed the construction of Excelsior Boulevard/Phase 2 Monterey Avenue to
France Avenue, as per Contract No. 14-98.
2. The Director of Public Works has filed his recommendations for final acceptance of the work.
3. The work completed under this contract is accepted and approved. The City Manager is
directed to make final payment on the contract, taking the contractor's receipt in full.
Reviewed for Administration:
Attest:
Ada
ted by the City Council October 7, 2003
' )/
yor