HomeMy WebLinkAbout95-8 - ADMIN Resolution - City Council - 1995/01/03f
1
95-8
RESOLUTION NO.
RESOLUTION ACCEPTING WORK ON
CONCRETE PIERS AND WATERMAIN ABANDONMENT
CITY PROJECT NO. 94-25A
CONTRACT NO. 3098
BE IT RESOLVED by the City Council of the City of St. Louis Park,
Minnesota, as follows:
1. Pursuant to a written contract with the City dated August 26,
1994, Minger Construction, Inc. has satisfactorily completed the improvements
of concrete piers and watermain abandonment as stated in Contract No. 3098.
2. The Acting Director of Public Works has filed his recommendations
for final acceptance of the work.
3. The work completed under this contract is accepted and approved.
The City Manager is directed to make final payment on the contract, taking the
contractor's receipt in full.
Adopted by the City Council January 3, 1995
Attest:
Reviewed for administration:
Approved as to form and execution:
44M4gL77014Cr—_
City Attorney