RESOLUTION NO. 92-140
RESOLUTION PERTAINING TO SUPPLEMENTAL AGREEMENT NO. 6
FOR IMPROVEMENT PROJECT NO. 89-05
(S.P. 2706-166; S.A.P. 163-276-24; S.A.P. 16-010-30)
TRUNK HIGHWAY 7/LOUISIANA AVENUE
CONTRACT NO. 2005
WHEREAS, the City Council entered into Contract No. 2005 with C.S. McCrossan,
Inc., for the construction of Improvement Project No. 89-05 (S.P. 2706-166;
S.A.P. 163-276-24; S.A.P. 16-010-30); and
WHEREAS, due to delays during the 1991 construction season caused by
snowstorms resulted in the postponement of a significant portion of the work until
1992; and
WHEREAS, the C.S. McCrossan, Inc. has requested additional compensation to
complete the contract; and
WHEREAS, representatives of the Minnesota Department of Transportation have
concurred with the C.S. McCrossan, Inc. request of additional compensation for
completion of the contract.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL of the City of St Louis
Park, that the request of C.S. McCrossan, Inc. for additional compensation is
hereby approved.
BE IT FURTHER RESOLVED BY THE CITY COUNCIL of the City of St. Louis
Park, Minnesota, that:
1. There is appropriated the sum of $42,476.83 for the additional costs.
2. City staff is directed to seek reimbursement from the Minnesota
Department of Transportation for all or any portion of said $42,476.83
to which the City may be entitled.
Adopted by the City Council September 8, 1992