HomeMy WebLinkAbout6991 - ADMIN Resolution - City Council - 1981/10/19RESOLUTION NO. 6991
A RESOLUTION GRANTING PERMIT UNDER SECTION 14-124.101 OF
THE ST. LOUIS PARK ORDINANCE CODE RELATING TO ZONING TO
PERMIT EXPANSION OF A TREATMENT CENTER FOR PROPERTY
LOCATED IN THE PUD, PLANNED UNIT DEVELOPMENT DISTRICT,
AT 3705 PARK CENTER BOULEVARD
BE IT RESOLVED BY the City Council of the City of St. Louis Park:
Findings
1. Parkview Centers, Inc. has made application to the City Council for
a special permit under Section 14-124.101 of the St. Louis Park Ordinance
Code for the purpose of expanding a treatment center located at 3705 Park
Center Boulevard for the legal description as follows, to -wit:
That part of Lot 2, Block 2, PARK CENTER, according to the recorded
plat thereof, described as follows:
Commencing at the intersection of the east line of said Lot 2 and
a line 24.00 feet northerly of, measured at a right angle to and
parallel with the south line of said Lot 2; thence westerly, along
said parallel line, a distance of 423.00 feet; thence northerly,
parallel with said east line, a distance of 401.00 feet to the
beginning of a line hereinafter described as "Line A"; thence
northwesterly deflecting to the left 16 degrees 35 minutes 14
seconds, to the southerly right-of-way line of Park Center
Boulevard as dedicated in said plat of PARK CENTER and said
"Line A" there terminating; thence easterly, along said southerly
right-of-way line, to the intersection with a line 60.00 feet
easterly of, measured at a right angle to and parallel with
said "Line A" and the point of beginning of the land to be
described; thence southeasterly, along the last described
parallel line, to the intersection with a line drawn westerly,
parallel with the south line of said Lot 2, from a point on the
east line of said Lot 2 distant 401.00 feet northerly from the
point of commencement; thence easterly along the last described
parallel line, to east line of said Lot 2; thence northerly,
along said east line, to the northeast corner of said Lot 2;
thence westerly, along the north line of said Lot 2, to the
easterly right-of-way line of Park Center Boulevard; thence
southerly and southwesterly, along the easterly and southeasterly
right-of-way line of said Park Center Boulevard to the point of
beginning.
2. The City Council has considered the advice and recommendation of
the Planning Commission (Case No. 81 -91 -SP) and the effect of the proposed
expansion of a treatment center on the'health, safety and welfare of the occu-
pants of the surrounding lands, existing and anticipated traffic conditions,
the effect on values of properties in the surrounding area, the effect of the
use on the Comprehensive Plan, and compliance with the intent of the Zoning
Ordinance.
3. The Council has determined that the proposed expansion will not be
detrimental to the health, safety or general welfare of the community nor
will it cause serious traffic congestion nor hazards, nor will it seriously
depreciate surrounding property values, and the proposed expansion is in harmony
with the general purpose and intent of the Zoning Ordinance and the Comprehensiv
Plan.
Conclusion
The special permit to permit expansion of a treatment center at the location
described is granted based on the findings set forth above and subject to the
following conditions:
1. That the site be developed, used and maintained in
accordance with Exhibit A, Landscape and Grading Plan;
Exhibit B, Elevation Plan; Exhibit C, Sheet 1 and 2,
Floor Plans, New Addition; Exhibit J, Original Elevation
Plan; and Exhibit K, Floor Plan, Original Construction.
2. That all utilities be placed underground and there be
no outdoor storage of trash or materials.
3. That the site be used as a medical treatment center for
63 beds (35 beds in the old addition and 28 beds in the
new addition), ancillary facilities, and corporate offices.
4. That a five foot wide sidewalk be constructed approximately
five feet off from the curb line tying to the existing
sidewalk adjacent to Byerly's and extending to the easterly
limits of the property.
5. That the curbing in the parking lot be poured in-place
concrete curbing measuring at least six inches above
grade.
6. That a Contract for Private Development be executed
with the Housing and Redevelopment Authority.
7. That all improvements including buildings, landscaping,
parking, utilities, sidewalk, curbing, and all other
elements contained on the exhibits be completed by
May 15, 1983.
Adopted by the City Council October 19, 1981
ATTEST:
viewed by administration:
CF y Manager
Approved as to form and legality:
City Attorney
2
fd-6,0 z